- The proposal
- Fourth NPL edition at Gautam Buddha International Cricket Stadium in Bharatpur, Chitwan, if floodlights and technical work are completed in time
- Construction status
- 68 per cent complete; both tower structures finished, parapet work 80 per cent done, subsurface drainage under way; infrastructure finished within four months, officials say
- Capacity
- 15,000 spectators after phase one, rising to 30,000 after phase two; five pitches planned, against seven at the TU ground in Kirtipur
- Cost and timeline
- First-phase contract Rs 862.484 million, up from Rs 785.091 million; 30-month contract expires 11 January, with two further months estimated to finish
The fourth edition of the Nepal Premier League could be played away from Kirtipur for the first time, at a ground that has waited years to be finished. Gautam Buddha International Cricket Stadium in Bharatpur, Chitwan, is 68 per cent complete, and officials say that if floodlights and the remaining technical work are delivered, the venue could host NPL matches in around a year.
It would be the most visible change the league has seen since it began. Every match of all three seasons so far, 32 games in the third edition alone, has been played at the same ground, the Tribhuvan University International Cricket Ground in Kirtipur. The idea of taking the tournament to the cities whose names are on the teams has been discussed for years, but it stayed an idea because no ground outside the capital was ready. Chitwan now looks closer to ready than any of them, and the people building it are talking about next season, not some distant future.
A ground nearly ready, and a league ready to move
The push comes from the top. On the day the third edition ended, with Sudurpaschim Royals lifting the title in Kirtipur, Prime Minister Balendra Shah announced that all eight clubs would get floodlit home grounds and that the league would be played home and away. On Tuesday, Infrastructure Development Minister Sunil Lamsal sat down with representatives of all eight franchises to discuss how that promise becomes a schedule, and Chitwan was at the centre of the conversation.
Chitwan Rhinos chairman Ayush Neupane came out of the meeting optimistic. He said the minister was positive about the proposal, and that the discussion had covered playing matches in Chitwan and at Mulpani next year. The stadium's construction could be completed within a few months, he said, and if the federal government provides the floodlights and completes the technical infrastructure, there would be no problem hosting matches there. The prime minister has already designated the Gautam Buddha ground as the home of the Chitwan Rhinos, so the club's case is not starting from scratch.
For the Rhinos, the argument is also about geography. Neupane pointed out that Chitwan would be a convenient base for franchises from Janakpur, Lumbini and Pokhara, all of which sit within easy reach of Bharatpur. A ground in Chitwan would not serve one club alone. It could host matches for several teams from the southern plains, and give supporters in the Terai their first chance to watch the league at home.
What is finished, and what is left
The numbers behind the optimism come from Bharatpur Metropolitan City, which owns the project. Acting mayor Chitrasen Adhikari said the stadium's infrastructure could be completed within four months, and that around 68 per cent of the overall construction work is already done. Both tower structures are complete and finishing work is under way. The seating in the parapet is finished, concreting is being prepared behind it, and the parapet work as a whole is about 80 per cent complete.
Work on the playing surface has reached the stage every ground project waits for. Pipes for the subsurface drainage system are being laid, and once that work is finished, gravel will go down before the pitch is built. The drainage and compound wall works are already complete. When the first phase finishes, 15,000 spectators will be able to watch from the stands. The metropolitan city plans to proceed gradually with the second phase, which will raise the capacity to 30,000.
Those numbers matter because they answer the complaint that has followed the league since its first season. The TU ground in Kirtipur holds only 10,000 spectators, and three seasons of sell-out crowds have made that limit impossible to ignore. A 15,000-seat ground in Chitwan, growing to 30,000, would be the biggest cricket venue in the country by a distance. The trade-off is in pitches: the TU ground has seven, while the Gautam Buddha ground will have five, so a Chitwan leg would need tighter scheduling than Kirtipur allows.
The long road to Bharatpur
The stadium has been a long time coming, and its history explains why nobody in Chitwan is counting on promises alone. The project began with an agreement between the Dhurmus-Suntali Foundation and Bharatpur Metropolitan City on 16 Magh 2075, and preliminary construction started in Mangsir 2076. Work stopped in 2078 after the foundation could not raise the money it needed, and the ground sat unfinished for years before ownership passed to the metropolitan city.
The restart came on 24 Asar 2081, when Bharatpur awarded the first-phase construction contract to Himalayan JV. The contract gave the builder 30 months, and that period expires on 27 Poush, 11 January. The acting mayor estimates the remaining work will take about two more months beyond that, which puts completion in the first months of next year, comfortably before the fourth edition is due.
The cost has grown with the delays. The original contract was worth Rs 785.091 million, and the amount has since risen to Rs 862.484 million. Completing the second phase will need roughly Rs 2 billion more for civil construction work alone, excluding floodlights. The acting mayor's message to the federal government was direct: if it provides the extra infrastructure and installs the floodlights, the next edition of the league can be played in Bharatpur. He added that the ground is well placed geographically, and could even host matches involving neighbouring countries.
Why Chitwan, why now
The case for Chitwan is being made by more than the people building the ground. Anil Adhikari, the cricket director for Bagmati Province, has argued strongly that the fourth edition should be held in Bharatpur, and says he is confident it will happen because the government is positive about the proposal. His argument is built on a comparison with Kirtipur: seating and floodlights were installed at the TU ground within nine months, and with 11 months available in Chitwan, he asked why the same could not be done there.
Adhikari also sees a bigger future for the venue than one league season. He said the stadium would be capable of hosting national and international matches, and described Bharatpur as a convenient location for players from districts across the Terai. Suraj Gyawali, secretary of the Chitwan District Cricket Association, said the stadium is being built to the required standards and called for collective support to bring the fourth edition to the city. Hosting the tournament there is possible, he said, and with the government showing a positive response, he is confident it can happen.
The practical case is strong too. Gyawali noted that matches involving clubs from neighbouring districts could also be organised at the venue, and that Bharatpur is within easy reach for Pokhara, Lumbini and Janakpur. The city has adequate hotels for players and spectators, and when there is no match to watch, visitors have Chitwan National Park and the district's other attractions on their doorstep. For a league that has sold out every big game it has staged, a host city that can feed, house and entertain a travelling crowd is part of the pitch, not an afterthought.
What still has to happen
None of this is settled yet. The floodlights and the technical work are the federal government's part of the deal, and the commitment to deliver them has not been made. The stadium's own construction still has months to run, the contract deadline arrives in January, and the second phase, with its Rs 2 billion civil bill, is a separate project that will take far longer. What Chitwan has is a ground that is visibly close to finished, a set of officials speaking with one voice, and a minister who has now heard the case in person.
The next signs to watch are concrete. Whether the federal government commits to the floodlights and the technical infrastructure, whether the first-phase work finishes on the acting mayor's timetable after the January deadline, and whether Chitwan is named among the first venues when the phased home-and-away plan takes shape. The wider stadium programme still has its funding questions to settle, and the cost and revenue framework for the new grounds has yet to be drawn up.
If those pieces fall into place, the fourth edition will open with something the league has never had: a second home. A floodlit evening in Bharatpur, in front of 15,000 people, would be the first proof that the tournament can leave Kathmandu and still feel like the same league. If they do not, Chitwan will have a nearly finished stadium and a familiar wait. Either way, the ground that spent years as a symbol of stalled ambition is now, for the first time, being talked about as a venue with a date attached.
FAQs
Can the fourth NPL edition be played in Chitwan?
Possibly. The stadium is 68 per cent complete, and officials say matches could be held there in around a year if the federal government installs floodlights and finishes the technical work. The final decision will depend on that commitment and on construction finishing on schedule.
How many spectators will Gautam Buddha Stadium hold?
The first phase will seat 15,000 spectators, and the second phase will raise the capacity to 30,000. The TU Cricket Ground in Kirtipur, which has hosted every NPL match so far, holds only 10,000.
When will construction of the stadium finish?
The 30-month first-phase contract expires on 11 January, and Bharatpur's acting mayor estimates about two more months will be needed to finish the remaining work. He said the stadium's infrastructure could be completed within four months.
What will the Gautam Buddha Stadium cost?
The first-phase contract was originally worth Rs 785.091 million and has risen to Rs 862.484 million. Completing the second phase will need roughly Rs 2 billion more for civil construction work, excluding floodlights.